We'll keep you up to date on progress, when we hit construction milestones and when you need to take any action.
Looking ahead, the following works are planned over the coming weeks:
The construction team continues to make excellent progress, and we appreciate your ongoing support. We look forward to sharing further updates, which will now become more regular as we move closer to completion. We will start to outline timeframes, that will help prepare you for pre-settlement inspections as well as starting conversations with your lenders /broker, etc.
Hindmarsh are making great progress on the construction of Woden Green, with many milestones achieved to date and all three towers coming out of the podium.
• WG1 is the leading tower, currently up at Level 5 and targeting to be at Level 9 in June.
• WG2 is sequenced closely behind, currently completing formwork to Level 4 and targeting to be formed to level 8 in June.
• WG3, the final stage of Woden Green, is currently completing formwork to Level 3, targeting to be at Level 6 in June.
Precast façade panels are currently being installed across all towers, and shortly fitout and glazing will commence at the lower levels. The basements have had the stripping of formwork completed in Basement Levels 2 & 3, and throughout part of Basement Level 1 and Ground.
By end June, we will be targeting to raise Tower Crane 1 as we move through the higher levels of the towers!
Whilst the above gives an overview of some key milestones that have been achieved, the below photos give a real visual and appreciation into the progress being made on site. We have outlined the podium level in orange to illustrate the first level of apartments. We hope you enjoy this update, and we look forward to welcoming you home to Woden Green in mid-2025!


Here are some photos to demonstrate the spectacular views in all towers, at all levels, in all directions.
If you have any questions, get in touch with your agent.